Fault 3P HV F7

DC/DC_Softstart_Fault

DC/DC soft-start fault

EcoBSS service: DC/DC soft-start / BUS cannot build.

Register map

Family
Three-phase HV
Register
555
Bit
6

Field checks

  1. BUS voltage cannot be established from PV or from energy storage.
  2. Restart the inverter; if the fault remains, contact Inversol.

FAQ

What does EcoBSS F7 mean?
DC/DC soft-start fault
What should I check for EcoBSS F7?
  1. BUS voltage cannot be established from PV or from energy storage.
  2. Restart the inverter; if the fault remains, contact Inversol.
When should I contact Inversol?
Confirm LV vs HV family on the nameplate, complete the field checks, then contact Inversol with model, SN, family, and a photo if the code returns after a clean power cycle.

Partner lookup from EcoBSS Flex register map V1.2 — not a substitute for the official service manual or live measurements. Always match the inverter family (3P LV / FLEX 3L vs 3P HV).